Sorry! We could not find your page. Perhaps searching can help.
Page not found – Pakissan.com
Oops, page not found
Sorry! We could not find your page. Perhaps searching can help.
ISSUES
Facts about
Thal flood water canal
The Exective Committee of the
National Economic Council (Ecnec) in its meeting held on 28th
February 2002 approved the Thal Flood-Water Canal Project at a
cost of Rs30.5 billion. The project is divided into two
phases, the first to cost Rs21.8 billion and the second one
Rs8.6 billion.
The two phases are spread over five stages. The difference
between a stage and a phase is hazy at best, because according
to the Concise Oxford Dictionary, stage is a point or period
in development, or a process, whereas a phase is a stage of
change or development. Although the period of completion is
seven years involving five years for Phase-I and two years for
Phase-II, completion date is 30 June 2008. (This may be
because the project was started a year before its approval by
the Ecnec.) Annual recurring expenditure for maintenance after
completion has been estimated at Rs142 million.
The sponsoring agency is the ministry of water and power, the
executing agency is Wapda and the beneficiary is the
government of Punjab, which will have the ultimate
responsibility for operations and maintenance. The project
covers 4 districts i.e. Bhakker, Layyah, Khushab and Jhang -
all in Punjab with a population is 570,000. The proposed canal
takes off from a head regulator at Adhi Kot of Chashma-Jhelum
Link Canal where a regulator has been constructed. The gross
cultivable area (GCA) of the project is 1.9 million acres and
culturable command area (CCA) is 1.53 m acres.
Phase
Channel to
be Constructed
Starting Year
Commissioning Year
Lengths of
Channel (Miles)
Main Canal Branch
Distys And
Minors
I
Main Canal, Mankera
Branch, Chaubara Branch Dhingana Branch and their
distribution System.
1
5
112.4
485.1
II
Nurpur Branch, Mahmood Sub
Branch and their distribution system.
5
8
133.4
742.2
TOTAL
245.8
1227.3
In physical terms, the irrigation system will consist of one
main canal, four branches namely Mankera, Chaubara, Dhingata
and Nurpur, and one sub-branch Mahmood besides few minors
having a total length of 1,475 miles. The length of main and
branch canals will be 246 miles, of distributaries and minors
1227 miles, and irrigation channels 1473 miles. It will have
823 structures like regulators, bridges etc. There will be 152
head-and cross-regulators, 29 fall structures, 119 falls
structures with road crossings, 2,8391 road bridges and 2,741
outlet structures. 79,962 acres of land will need to be
acquired. Fifty-eight jeeps and 34 pickups will provide the
much needed responsibility. Moreover, residential and
non-residential buildings and other related civil works would
also be built. Not much resettlement will be involved, that
having been characterized as 'insignificant' in the PC1. The
table below shows the details:
Time for construction and related
agricultural developments is given in Table 2:
Phase
Canal/Channel System
GCA (000
Acres)
CCA (000
Acres)
Agricultural Development Starts in Project Year
Ultimate
Agricultural Development Achieved in Prject Year
I
Main Canal
and Mankera Branch
4.19.9
336
5th
14th
Chaubara
Branch
324.9
259.9
5th
14th
II
Dhingana
Branch
547.7
438.2
5th
14th
Mahmood
Sub-Branch
301.8
241.4
8th
17th
Nurpur Branch
323.7
259
8th
17th
TOTAL
1918
1534.5
Summary of project cost estimate is
given in Table 3:
S. No.
Category/Item
Total Cost
(Rs.)
Project
Phase-I
Project
Phase-II
1
Civil,
Mechanical and Electrical
14,058,362
10,795,117
3,263,246
2
Other Works
5,661,101
3
Interest
during construction
3,868,620
2,698,560
1,170,060
4
Administration & Contingencies etc.
6,879,026
8,377,003
4,163,123
TOTAL
30,467,109
21,870,680
8,596,426
The Project's feasibility has been
assumed as given in Table 4:
Present Worth
of Benefits
28151.46
Present Worth
of Cost
15532.72
Net Present
Value (NPV)
12618.69
B.C. Ratio
1.81
EIRR
(Percent)
18.46
Contrary to the name of the project, Thal Flood-Water Canal,
most of the water will come out of allocation for 'Greater
Thal Canal', as provided under the Water Accord 1991 and not
from floods. Only supplemental water will come from floods
between 1st June and 1st September of every year. Table 5
gives in precise mathematical terms the availability of water
year in year out: Table 5:
Ten Daily periods
NON PERENNIAL IRRIGATION
ALLOCATION ONLY (From
Punjab Share)
ADDITIONAL FLOOD SUPPLIES
TOTAL
1-JUNE
5.4
3.1
8.5
2
5.5
3.0
8.5
3
5.8 (5.7)
2.8
8.5
1-JULY
5.8
2.7
8.5
2
5.1
3.4
8.5
3
4.7
3.8
8.5
1-AUG
4.8
3.7
8.5
2
5.4
3.1
8.5
3
5.9
2.6
8.5
1-SEP
5.9
2.6
8.5
It has been assumed in the Table 5 that the flood supplies
between June and September on ten daily basis will be such as
to make the total together with Punjab's allocation exactly
8.5 cusecs. The haste in arriving at the magic figure of 8,500
cusecs under all circumstances is apparent from the fact that
for the third ten days of June, the allocation has been
mentioned as 5.8 cusecs as against the actual allocation of
5.7 cusecs.
The Indus River System Authority (IRSA) has granted no
objection certificate in the following words: - "The
recommendations regarding availability of water, against the
Para 2 and Para 4 uses apportioned to the Punjab canal in
Water Accord, have made by 4:1 majority decision under sub
section 92), section 8 of the IRSA Act (Member (Sindh)
dissenting), as shown on the statement attached."
This recommendation was made under Water Accord 1991 whereby
IRSA can "make recommendation on the availability of water
against the allocated areas of the provinces". Thus the
project is dependent on share of water of the Punjab province.
The other objection that Sindh raises is that the proposed
canal is being implemented under the Water Accord 1991, which
the Government of Punjab has failed to honour. Getting back to
the Accord, the availability is dependent upon the exaggerated
water availability of 114 MAF, as promised under the Accord.
It has usually been 103 MAF. As a matter of fact, the data for
Kharif 2000-01 indicates that shortages with reference to the
Accord were as high as 57 per cent for early Kharif and 29 per
cent for late Kharif
This being a non-perennial canal, it is designed to provide
irrigation water from 1st April to 30th September to the
extent of 2.496 MAF. Out of this 1.873 MAF will be available
under Inter-Provincial Accord 1991 from Punjab's own share and
0.624 MAF have been assumed as flood supplies during the
monsoon period of four months.
The voluminous PC-I, surprisingly, does not provide any data
on floods to support the assumed availability of water during
the four months. If there are no floods, there will be no
water. It should be interesting to know if any of the senior
civil servants in the ministries of water and power or
planning and development or finance departments objected to a
hasty and hurried approval of this project and whether an
objection was raised to the award of two contracts prior to
the approval of the PC-I.
As a matter of fact, even if floods conform to the optimistic
assumptions of the estimators, the water availability under
the Accord is in itself in serious doubt. Allocation to Punjab
was made for Greater Thal, and not for this project, i.e. Thal
Flood Water Canal. But somehow, Greater Thal metamorphosed
into 'Thal Flood Water Canal'.
The name would make sense only if the entire project were
flood based.. The project has been approved by the ECNEC
without its feasibility having been established. Since the
project has been put under implementation before its approval,
in case, the project is determined to be non-viable after the
feasibility report, the responsibility for the loss to the
exchequer for the unauthorized execution will have to be
clearly outlined.
There have been howls of protest, particularly in the province
of Sindh. The Sindh government through a letter of 7th March
2002 has protested against the approval of the project and has
alleged bad faith in as much as the project document was
received by Sindh three days after it had been cleared by the
Central Development Working Party (CDWP). The Sindh government
received the minutes of the meeting of the CDWP two days after
they had been considered by Ecnec. Sindh received the project
summary for the Ecnec on 26th February 2002, i.e. two days
before its consideration.
Sindh has also expressed the apprehension that little or no
water will be available for 'escapage' into the sea below
Kotri, if it is used in the proposed canal; and the area will
be destroyed with serious ecological, economic and social
consequences. The mangroves in that area are a national
heritage in spite of their location in Sindh.
Sindh has objected to this canal also on the ground that there
is already a serious shortage of water in the country.
Construction of a huge canal would aggravate the shortages for
the areas under cultivation. The province's agriculture is on
the brink of disaster and famine-like conditions prevail. It
has also been stated that the canal will take off from
Chashma-Jhelum Link Canal (C-J Canal), which itself is a great
burden on Indus water system. Originally built to divert
floodwater, C-J Canal is actually being run by Punjab for the
year round. It is, therefore, feared by Sindh that the new "Thal
Flood Canal", originally named as "Greater Thal Canal", will
also be run for full year.
The project has been hastily conceived and rushed through the
planning process without observing prescribed formalities. So
much so that its feasibility report is not yet ready.
According to the quarterly report referred to above, PC-II was
under way when 25 per cent physical works had been completed
against 30 per cent target by October 2001 (Please note that
the report review period ended September 30).
According to Quarterly Progress Report on ADP Projects, for
the period ending 30 September 2001 (six months back), a
review of Greater Thal Canal (now Thal Flood-water Canal)
indicated that, an allocation of Rs. 500 million had been made
for the year and Rs. 50 million released. Rs. 7.8 million were
spent. The carelessness with which the unapproved project was
taken up is apparent from the fact that it was estimated in
the same report to cost Rs25 billion (page 19) Rs 28 billion
(page 18), Rs30 billion (page 17). It was finally approved for
Rs30.5 billion on 28 February 2002.
Excavation contract for first reach (5 km) had been awarded,
the contract for 2nd reach (15 kms) which was to be awarded in
January 2002, may have been awarded and acquisition of 400
acres of land by government of Punjab, which was on track, may
have been acquired. Tenders for structures and lining of Canal
are to be opened in September 2002. In that report it was also
stated that although the sponsoring agency was the ministry of
water and power, executing agency was Wapda, and yet the PC-I
was with the Punjab for submission to the Planning Commission.
The project has a long history. It has been under dispute
since 1871 when the British rejected it for two reasons: (a)
It would hit the vital interest of the lower riparian, i.e.
Sindh; and (b) The land to be brought under cultivation is
barren waste with no hope of producing anything.
In the recent past it was originally conceived as Greater Thal
project, but was permanently shelved by the Ecnec in it's
meeting on 19th August 1975. It formed part of " Kala Bagh Dam
and Allied Irrigation Scheme" and included Kala Bagh Right
Bank Canal, Kala Bagh Left Bank Canal, CRVC, CJ Link Canal
(existing) and Thal Canal (existing).
Since Kala Bagh Dam has become a subject matter of intense
provincial controversy, taking the proposed canal from
Chashma-Jhelum Link without Kala Bagh, which would provide the
required storage, is like putting the cart before the horse.
Once the Canal is constructed and remains dry, it is assumed,
the colossal expenditure on construction of the Canal together
with branches, the land acquisition and the dislocation
involved in resettlement all will be in vain.
Even if the assumed flood flows become available, a fat
chance, the floodwater cannot be monopolized by Punjab,
because the benefits of floods should accrue to other
provinces as well. Besides the huge expenditure of Rs30.5
billion over seven years period giving an average of more than
Rs 4 billion per annum, appears beyond the national resources
of the government of Pakistan. And even if the huge resources
could somehow be generated, their exclusive use in one
province militates against the principle of equity.
The latest physical progress is not known, but in the
meanwhile, it was reported on 19th March 2002 in the
newspapers, 'that all work had been ordered to be stopped'.
Nothing unusual in that! One could find a large number of
projects never completed in time or left in the middle.
Following is an illustrative list of mega projects that have
shown remarkable slippage's:
LIST OF PROJECTS REVISED
Rs.
Million
Name of Project
App.
Original
1st
Revision
2nd
Revision
3rd
Revision
4th
Revision
Cost
Date
Cost
Date
Cost
Date
Cost
Date
Cost
Date
Left Bank Outfall
Drainage Project
(LBOD)
8593.5
01.04.84
23,432
28.05.94
31036.6
06.09.97
33441.8
28.02.02
Upper Rechna
Remaining Deg
Drainage Project
231
31.12.89
695.3
27.7.95
1040.4
20.10.2000
Fordwah Eastern
Sadiqia Remaining
Phase-I Project
1067
29.10.88
2054.1
27.7.95
3295
Chashma Right
Bank Irrigation
Project (CRB)
1507.4
30.11.78
3477.6
23.02.82
10213.3
28.11.91
13869.9
22.11.98
17096.9
3.5.01
Courtesy Dawn March
26, 2002
Views presented
here are of those of the writer and Pakissan.com is not liable
them.
Page not found – Pakissan.com
Oops, page not found
Sorry! We could not find your page. Perhaps searching can help.