KARACHI,
JUNE 15, 2011: Sindh Irrigation Department has failed to
meet the deadline to complete 41 rehabilitation schemes of
Indus and non-Indus dykes, reliable sources told Business
Recorder on Tuesday.
High level officials of the irrigation department had
announced that they will complete work of rehabilitation of
Indus and non-Indus dykes till 31st of May 2011 but could
not complete the schemes on the given time.
Despite failing in achieving the target, many officials of
Irrigation department claimed that they have completed major
rehabilitation schemes, while the rest would be completed
till 30th June 2011 but the report compiled by irrigation
department disclosed that 'not a single scheme has been
completed yet'.
According to the irrigation department's report namely
"physical progress of flood protection works in Sindh up to
May 31st", obtained by Business Recorder, 92 percent work
has been done on the scheme of construction of new
Gorhaghat-Tori-Makhwani link Bund from mile 0/0 to 3/0
(first defence line at Tori Bund connecting Gotrhaghat to
Tori and Makhwani Bund) in Kasmore-Kandhkot, 35 percent work
has been done on scheme of restoration of stone apron mile
5/7+100 to 6/1+100 of Qadirpur loop Bund in Ghotki-Mirpur
and 46 percent work finalised on the scheme of raising and
strengthening of Qadirpur Loop Bund from mile 0/0 to 8/4 and
extension of stone pitching from mile 5/0 to 7/2, providing
stone pitching from mile 0/0 to 5/0 and 7/2 to 8/4 in
Ghotki-Mirpur.
The report further mentioned that 28 percent work has been
done on scheme of raising and strengthening of earthwork
along M.S Bund from mile 34.6 to 55.4 in Thatta, 52 percent
carried out on scheme of raising and strengthening of
earthwork along P.B Bund from mile 0/0 to 15/0 and providing
stone pitching from mile 4/4 to 5/5 in Thatta, 62% work has
been done on scheme of earthwork and providing stone
pitching and dumping stone at breach site (Kot Almoo) M.S
Bund from mile 18/1+150 to 18/3+30 in Thatta, 74 percent
work done on scheme of raising and strengthening of
earthwork along KBF Upper (River Bund from RD 35.0 to 145.0)
in Jamshor-Thatta and 38 percent work has been done on the
scheme of raising and strengthening and providing stone
pitching of Manchhar Containing Bank from Rd 0 to 100 in
Jamshoro-Dadu.
Besides, 71 percent work has been done on scheme of raising
and strengthening of earthwork and providing stone pitching
along S.H Bund from mile 0/0 to 3/2 R/S of earthwork and
stone pitching along all Bahar Bund from mile 0/0 to 2/2 and
raising and strengthening of earth work and providing stone
pitching along Hillaya Bund from mile 0/0 to 0/6 in Thatta,
79 percent work carried out on scheme of Stone pitching of
remodelling of Surjani Bund mile 0/0 to 1/7 in Thatta, 16
percent work done on scheme of raising and strengthening of
Bandar walls and Bunds in Barrage division of Sukkkur, 70%
work has been done on recoupment stone apron Aqil Loop Bund
Mile 2/0 to 2/5 in Larkana and 39 percent work done on
raising and strengthening of Larkana-Sehwan Bund from mile
77/2 to 102/0 and providing stone pitching from mile 84/0 to
92/0 in Jamshoro-Dadu.
Report added that 31 percent work has been done on
construction of stone pitching along S.M mile 0/5 to 2/4,
front Bund mile 0/0 to 3/, S. M Bund, mile 7/4 to 8/4, stone
pitching Kandiyaro scape RD 26 to 29 R/S and RD 28 to 52,
L.S Bund mile 40/0 to 42/0 and 45/0 to 46/0, 51/0 to 52/0
and RD 54/0 to 57/1, 61/0 to 63/0 and 64/0 to 65/0 and 74/4
to 78/5 in Khauirpur-Naushehroferoze, 58 percent work done
on raising and strengthening closing breach, repair to stone
pitching and bund sluice along Suprio Bund Rd 0 to 95 in
Dadu, six percent work done on reconstruction of Danstar
Head Regulator in Jamshoro, 78 percent work done on raising
and strengthening and providing stone pitching along F.P
Bund Rd 0 to 220 including closing breach Rd to 147 in Dadu
and 43 percent work has been done on raising and
strengthening and providing stone pitching along F.P Bund RD
346 to 395 (Hamal lake portion ) including closing 4 No
breaches RD 483 to 485 in Qambar-Shahdadkot.
Similarly, 84 percent work has been done on scheme of
Extension of trench Bund with stone pitching, raising and
strengthening from mile 7/2 to 15/7 of left Marginal Bund of
Rahimyar Khan-Rajanpur, 65 percent work done on
re-sectioning of K.K Bund mile 10/0 to 14/3 and construction
diaphragm wall mile 12/4 to 14/3 in Kasmore-Kandhkot, 36
percent work done on re-sectioning of Kashmore Bund from
mile 19/2 to 21/6 and providing stone pitching from mile
20/7 to 21/6 and providing stone pitching from mile 20/7 to
21/7 and providing diaphragm wall from mile 19/2 to 21/6 in
Kasmore-Kandhkot, 55 percent work has been done on R&S of
Baiji Bund from 0/0 to 10/3 and providing stone pitching
from mile 6/4 to 10/3 in Sukkur, 44 percent work carried out
on scheme of R&S of L.M Bund (old) mile 0/0 to 6/0 and
raising of stone pitching mile 0/0 to 3/1 in Ghotki-Mirpur,
53 percent work has been done on recouping and construction
of stone pitching and earthwork along Ghallian front Bund
mile 0/0 to 12/7 in Hyderabad and 68 percent work has been
done on scheme of R&S of H.P Bund mile 0/0 to 20/0 providing
stone apron mile from 4/0 to 5/0+330 and providing and
raising stone pitching mile 9/0 to 12/4, 0/0 to 9/0 and 12/4
to 15/0 in Tando Mohammad Khan.
Although, the above mentioned report was till 31st May and
15 days have passed of June but the work is still continue
on all 41 schemes, sources told. Many officials of the
irrigation department were of the view that rehabilitation
schemes would not be finalised till 30th June 2011.
Due to this situation, growers of flood-hit districts are
not sowing crops because they are afraid that if floods will
come again, then continued work of rehabilitation would be
washed out. This scribe tried to get the version of
Secretary Irrigation, Khalid Hyder Memon regarding the
matter, but he neither was in office nor attended calls on
his mobile phone.
Courtesy: Business Recorder
|